Planning lifting equipment maintenance around your next shutdown

A planned shutdown gives maintenance teams access to equipment that may be difficult to take out of service during normal production. It also creates competing demands. Several contractors may need the same working area, replacement parts have to arrive in time and equipment must be available for the jobs that follow.

Lifting equipment deserves a place in those discussions early. If a hoist or essential accessory is unavailable when another maintenance task needs it, the effect can spread across the programme. A useful maintenance plan starts with understanding those dependencies.

Identify what the shutdown will need

Before booking servicing, establish which lifting equipment will be needed during the shutdown itself. An item due for maintenance may also be required to remove a motor, handle a component or support another contractor’s work.

For each critical item, record when it can be released and when it must be available again. Give someone responsibility for resolving clashes between maintenance work and operational demand. A single date in a diary rarely captures both requirements.

It is also useful to distinguish work that must be completed within the shutdown from work that can be organised beforehand. That gives the programme more room if an assessment identifies additional repairs.

Review condition before agreeing the work

Bring together the equipment details, manufacturer’s maintenance instructions and previous service information. Ask users to report problems they have noticed and pass those observations to the maintenance provider. Equipment with a suspected safety defect should be taken out of use and assessed promptly, rather than kept working until the shutdown.

This information helps the provider understand the proposed scope. It can also highlight questions about parts, access or the need for a more detailed assessment before a firm completion date is agreed.

Allow separately for thorough examination

Servicing and a thorough examination have different purposes. Maintenance keeps equipment in an appropriate condition; a thorough examination assesses safety-critical parts and records the findings. One does not automatically fulfil the other.

Where both are required, allow for both in the programme. HSE guidance also makes clear that the person undertaking the thorough examination should be sufficiently independent and impartial, and should not assess their own routine maintenance work. Organising the appointments together should still preserve that distinction.

Plan for equipment being unavailable

If an assessment identifies further work, the first question is often what that means for the next job. Discuss that possibility before the equipment is removed from service.

For some tasks, suitable hire equipment may provide temporary cover. For others, a replacement must meet a particular interface or operating requirement, so the options need closer consideration. Share the actual application with the supplier before assuming an available item can take its place.

Lift-Rite offers lifting equipment hire with technical support, as well as equipment sales. That provides a starting point for discussing temporary cover or replacement where either is appropriate.

Prepare the working area

Maintenance work needs safe access and suitable arrangements to protect people nearby. Agree site responsibilities, contractor access and any permits before work starts. Isolation and control of stored energy must be addressed through the appropriate safe system of work.

A practical booking should therefore include more than an arrival time. The maintenance provider needs to know when the equipment will be accessible and who can confirm that the work area is ready.

Agree what is needed before return to use

Set out the expected service records and handover information when commissioning the work. Include a route for reporting additional findings, authorising changes to the scope and confirming what remains outstanding.

The checks needed after repair depend on the equipment and the work carried out. Changes or repairs affecting critical parts may trigger a further thorough examination. Testing should be determined by the competent person with reference to the risks and manufacturer’s information; a proof load test is not automatically required after every service.

Build any required examination or testing into the return date. This helps everyone understand when an item will be ready for its next task, with the necessary work completed and records available.